The City’s contractor will start drainage construction on Tuesday, May 29th. Quail Run Road, between John King Blvd and FM-1141, will be closed to through traffic beginning on Tuesday, May 29th.  The road will be closed until mid-August.  The contractor will have signage in place.

The box culverts under Quail Run Road will be removed and replaced during the road closure.  Following the culvert installation, Quail Run Road east of John King will be reconstructed with asphalt for a distance of 600 feet.

If you have any questions or need information, please call Jim Raines, Construction Inspector, at (214) 543-3255, or Kathleen Lappen, City Project Manager, at (972) 771-7746. 